Newcraighall Site Update
As we get ready for a well earned break, we wanted to give an update on progress to the end of the year. Having only been on site for just over 12 months, we have made some great progress!
Phase 1
-Timber kit, roof, and windows now complete across all 3 blocks
-Brickwork fully complete on all 3 blocks along with PVs.
-1st fix trades are nearing completion in Blocks 1 & 2 and will turn their focus to Block 3 in the new year. - 2nd fix will commence in Block 1 & 2 in the new year also.
Phase 2A
-Block 14 & 15 are watertight, with PV panels, windows, and roof tiling all complete
-Brickwork is also nearing completion on both blocks and internally 1st fix is well progressed.
-Timber kits for Blocks 16 & 17 are complete with the roofing well underway and windows due to be installed prior to the break.
Phase 2B
-Foundations for this phase are nearly complete however the shorter days and wet weather has slowed progress
Phase 4
-Piling is complete
Externals
-Drainage within the site is complete and road construction progressing well, with large areas of tarmac now complete. Further road construction remains ongoing
Phase 5
-There has been great progress with the BTR units which form Phase 5 of the development, with the foundation complete at Blocks 11 and 20. -The timber kit for Block 11 is making great progress, with Block 20 now on site and progressing -Piling complete for the flatted block.
Great work from the entire team - we look forward to making further progress on site next year as we start to complete and handover the first units!